  -When estimating the duration of a task, the project manager makes three time estimates for the task and then assigns a(n) ____________________, which is an importance value, to each estimate.
-When estimating the duration of a task, the project manager makes three time estimates for the task and then assigns a(n) ____________________, which is an importance value, to each estimate.


Definitions:

Mobile Tablets

Portable computing devices featuring touch screens ranging in size, utilized for various applications from web browsing to media consumption.

Two-Way Communication

Two-way communication is an interactive form of communication where information flows back and forth between parties, allowing for feedback, engagement, and mutual understanding, enhancing relationship building and problem-solving.

Facebook

A social networking platform that enables users to create profiles, share content and connect with people globally for both personal and business purposes.

Dialogue

A conversation or exchange of ideas and opinions between two or more parties, encouraging mutual understanding and problem-solving.

Related Questions