Critical Path
The longest sequence of tasks in a project that must be completed on time for the whole project to be finished by its deadline, determining the shortest possible project duration.
Crashing
The process of reducing project duration by adding extra resources to project activities, often resulting in increased cost.
PERT
Program Evaluation and Review Technique; a project management tool used to schedule, organize, and coordinate tasks within a project.
CPM
Critical Path Method, a project management technique used to estimate the duration of a project and determine the activities that are critical to project completion.
Q30: The second fundamental theorem of welfare economics
Q30: What three questions should you ask in
Q36: A measure of the degree of correlation
Q37: Which of the following should be the
Q55: In the 1961-2015 Canadian data, the inflation
Q72: Which written medium should be used when
Q99: Readers can get a more out of
Q105: Companies that are succeeding in social media
Q148: What is the name of the file
Q153: To increase the sophistication of your message,make