A project consists of nine major activities,as shown.There are three separate paths in the network: a-c-f,b-d-g,and e-h-i.
(i)What is expected project duration time?
(ii)Determine the probability that the project will take more than 35 weeks to complete.(All durations are in weeks.)
11eab92b_c477_d00e_99e6_ad14123209e7
Job Specialization
The process of focusing one's occupational concentration on a specific area of expertise, making the individual more adept at a particular task.
Motivator-Hygiene Theory
The Motivator-Hygiene Theory, proposed by Frederick Herzberg, suggests that job satisfaction and dissatisfaction arise from two different sets of factors: motivators, which can create job satisfaction, and hygiene factors, which can prevent dissatisfaction but not necessarily create satisfaction.
Job Content
The specific tasks, responsibilities, and duties that make up a particular job.
Working Conditions
The environment in which an individual works, including aspects such as safety, amenities, workload, and physical conditions.
Q5: The frequency of breakdown of a piece
Q10: Monte Carlo simulations yield approximate rather than
Q12: The degree of technology involved is a
Q16: Great Product,Ltd.has just received an order for
Q29: In waiting-line analysis,queue discipline refers to the
Q32: The total time needed to complete a
Q43: The EOQ with quantity discounts model,focuses on
Q47: A relatively simple tool for planning and
Q64: An advantage of JIT cross-trained workers is
Q101: Which of the following is not a