Activity 7 is directly preceded by two activities-activity 5 and activity 6.Activity 5 has an expected duration of five and an ES time of six.Activity 6 has an expected duration of seven and an ES time of seven.Activity 7 has an expected duration of 10.The ES for activity 7 is: