The Project Manager Is About to Begin a Project Comprised

question 17

Multiple Choice

The Project Manager is about to begin a project comprised of the following six activities: The Project Manager is about to begin a project comprised of the following six activities:   What is the estimated expected (mean) duration for project completion? A) 100 days B) 140 days C) 199 days D) 200 days E) 440 days What is the estimated expected (mean) duration for project completion?