Great Product,Ltd.has just received an order for 100 Whozats,which must be ready for delivery at the start of week six.An MRP planner has prepared the following table showing product structure,lead times (orders are lot-for-lot) ,and quantities on hand: What is the net requirement for Whatzats to fill this order?