Develop a Solution for the Following Line Balancing Problem, Allowing

question 51

Essay

Develop a solution for the following line balancing problem, allowing a cycle time of 5 minutes.
a. Draw the precedence diagram for the set of tasks.
b. Calculate the theoretical minimum number of workstations.
c. Balance this line using the longest task time heuristic.
d. What tasks are assigned to which stations?
e. Does the solution have the minimum number of stations? Explain.
f. How much idle time is there, summed over all workstations?
g. What is the efficiency of this line?
Develop a solution for the following line balancing problem, allowing a cycle time of 5 minutes. a. Draw the precedence diagram for the set of tasks. b. Calculate the theoretical minimum number of workstations. c. Balance this line using the longest task time heuristic. d. What tasks are assigned to which stations? e. Does the solution have the minimum number of stations? Explain. f. How much idle time is there, summed over all workstations? g. What is the efficiency of this line?


Definitions:

Sensation

The process by which our sensory receptors and nervous system receive and represent stimulus energies from our environment.

Average Threshold

The point at which a stimulus is of sufficient intensity to begin to produce an effect or to elicit a response.

Human Vision

The ability of the human eye to detect and interpret surroundings by processing information contained in visible light.

Candle Flame

The visible part of a candle light, produced by the hot, glowing combustion of the candle wick and wax.

Related Questions