A partially solved PERT problem is detailed in the table below. Times are given in weeks.
A partially solved PERT problem is detailed in the table below. Times are given in weeks.    a. Calculate the expected time for each activity. Enter these values in the appropriate column in the table above. b. Which activities form the critical path? c. What is the estimated time of the critical path? d. What are the project variance and the project standard deviation? e. What is the probability of completion of the project after week 40? a. Calculate the expected time for each activity. Enter these values in the appropriate column in the table above.
b. Which activities form the critical path?
c. What is the estimated time of the critical path?
d. What are the project variance and the project standard deviation?
e. What is the probability of completion of the project after week 40?


Definitions:

Success

The achievement of a set goal, standard, or objective, commonly measured by factors such as profitability, achievement of objectives, or personal fulfillment.

Goodie Bags

Packages filled with gifts, promotional items, or samples, often given to attendees at events or customers as a gesture of appreciation.

Sternberg

A psychologist known for his triarchic theory of intelligence, which categorizes human intelligence into analytical, creative, and practical dimensions.

Practical Intelligence

The ability to solve everyday problems through adaptive or creative reasoning and learning from experience.

Related Questions