Examlex

Solved

An Activity on a PERT Network Has These Time Estimates

question 80

Multiple Choice

An activity on a PERT network has these time estimates: optimistic = 1, most likely = 2, and pessimistic = 5. Its expected time is


Definitions:

Labour Hours

The total number of hours worked by employees in a specified period, commonly used as a measure of labor input.

Cast Bronze Valves

Valves made from cast bronze material, often used in plumbing and industrial applications for controlling the flow of liquids or gases.

Labour Productivity

The measure of the efficiency of a person, machine, factory, or system in converting inputs into useful outputs.