A Project Being Analyzed by PERT Has 38 Activities, 16

question 116

Multiple Choice

A project being analyzed by PERT has 38 activities, 16 of which are on the critical path. If the estimated time along the critical path is 90 days with a project variance of 25, the probability that the project will be completed in 88 days or less is