Three Critical Path Activities Are Candidates for Crashing on a CPM

question 112

Essay

Three critical path activities are candidates for crashing on a CPM network. Activity details are in the table below.
Three critical path activities are candidates for crashing on a CPM network. Activity details are in the table below.    a. What is the crash cost per unit time for each of the three activities? b. Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost? c. Which activity should be the next activity crashed to cut a second day from the project's duration; how much is added to project cost? a. What is the crash cost per unit time for each of the three activities?
b. Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost?
c. Which activity should be the next activity crashed to cut a second day from the project's duration; how much is added to project cost?


Definitions:

Evaluation Efforts

The systematic process of determining the worth, significance, or value of an activity, project, or program, often through the collection and analysis of data.

Intervention Outcomes

The results or impacts of specific actions or interventions, which can be measured to assess their effectiveness in achieving desired goals or objectives.

Follow-up

Subsequent actions or inquiries to check on the status of something or to further ensure the completion of a task or resolution of an issue.

Worker

An individual engaged in an activity, especially in the context of earning an income.

Related Questions