Three Critical Path Activities Are Candidates for Crashing on a CPM

question 58

Essay

Three critical path activities are candidates for crashing on a CPM network. Activity details are in the table below.
Three critical path activities are candidates for crashing on a CPM network. Activity details are in the table below.    a. What is the crash cost per unit time for activity A? b. What is the crash cost per unit time for activity B? c. Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost? d. Which activity should be the next activity crashed to cut a second day from the project's duration; how much is added to project cost? e. Assuming no other paths become critical, how much can this project be shortened at what total added cost? a. What is the crash cost per unit time for activity A?
b. What is the crash cost per unit time for activity B?
c. Which activity should be crashed first to cut one day from the project's duration; how much is added to project cost?
d. Which activity should be the next activity crashed to cut a second day from the project's duration; how much is added to project cost?
e. Assuming no other paths become critical, how much can this project be shortened at what total added cost?


Definitions:

Normal

This term generally refers to the standard or default state of an object or condition, often used in the context of settings or modes.

Relational

Pertaining to or using a type of database management system (DBMS) that stores data in tables related by common fields.

Tabular

Relating to or arranged in a table or systematic arrangement of data in rows and columns for easy reference and analysis.

Attribute

A property or characteristic of a data element, object, or entity in programming, databases, and web development.

Related Questions