Eight Jobs Have Been Sequenced at a Single Work Center

question 119

Multiple Choice

Eight jobs have been sequenced at a single work center. Total processing time for the eight jobs is 34 hours and total flow time for the sequence is 85 hours. For this schedule, utilization is __________ and average jobs in the system is __________.