A manufacturer has the following jobs waiting on a single work center. The firm has not decided which dispatching rule to apply in order to prioritize the jobs and fix them into the schedule. Processing time in 15-minute time blocks and due date for each job are in the table below.
a. Complete the following table. Show your supporting calculations below.
b. Which dispatching rule has the best score for flow time? for work in process (jobs in the system)? for lateness?
c. Is there ANY sequence that can avoid all lateness? Explain or provide an example.
Average Fixed Costs
The fixed expenses of a company or project divided by the number of units produced, decreasing as production increases.
Diseconomies of Scale
The phenomenon where an increase in production leads to higher average costs per unit, often due to inefficiencies associated with scale of operation.
Output Rate
The output rate is the speed at which goods or services are produced over a specific period of time, often measured to evaluate productivity.
Fifth Worker
Refers to an addition to a workforce that exemplifies the impact or utility of hiring an additional employee in a given scenario.
Q5: Conventional MRP uses time buckets that do
Q21: A high school senior is seeking admission
Q25: The word "finite" in finite capacity scheduling
Q27: The theory of comparative advantage states that
Q45: Compare the assumptions of the production order
Q67: Which one of the following statements is
Q84: What does enterprise resource planning (ERP) allow
Q96: Normally, the transportation model is used to
Q124: Which one of the following is an
Q138: Which of the following files tracks work