Each X Requires 2 of Component Y; Each Y Requires

question 82

Multiple Choice

Each X requires 2 of component Y; each Y requires 4 of part Z. The lead time for assembly of X is 1 week. The lead time for the manufacture of Y is 1 week. The lead time for the procurement of Z is 6 weeks. The cumulative lead time for X is __________ weeks.