The network below represents a project being analyzed by the critical path method.Activity durations are A=5,B=2,C=12,D=3,E=5,F=1,G=7,H=2,I=10,and J=6. The network below represents a project being analyzed by the critical path method.Activity durations are A=5,B=2,C=12,D=3,E=5,F=1,G=7,H=2,I=10,and J=6.   a.What task must be on the critical path,regardless of activity durations? b.What is the duration of path A-B-E-H-J? c.What is the critical path of this network? d.What is the length of the critical path? e.What is slack time at activity H? f.What is the Late Finish of activity H? g.If activity C were delayed by two time units,what would happen to the project duration? a.What task must be on the critical path,regardless of activity durations?
b.What is the duration of path A-B-E-H-J?
c.What is the critical path of this network?
d.What is the length of the critical path?
e.What is slack time at activity H?
f.What is the Late Finish of activity H?
g.If activity C were delayed by two time units,what would happen to the project duration?


Definitions:

Diminishing Returns

Diminishing returns refer to a point at which the level of profits or benefits gained is less than the amount of money or energy invested.

Rental Price

The cost of leasing or renting a property or equipment, typically expressed on a monthly or yearly basis.

Tomb Of The Leopards

An Etruscan tomb in Italy, famous for its wall frescoes depicting a banquet scene with figures and leopards.

Related Questions