Three Critical Path Activities Are Candidates for Crashing on a CPM

question 22

Essay

Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.
Three critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.    a.What is the crash cost per unit time for activity A? b.What is the crash cost per unit time for activity B? c.Which activity should be crashed first to cut one day from the project's duration;how much is added to project cost? d.Which activity should be the next activity crashed to cut a second day from the project's duration;how much is added to project cost? e.Assuming no other paths become critical,how much can this project be shortened at what total added cost? a.What is the crash cost per unit time for activity A?
b.What is the crash cost per unit time for activity B?
c.Which activity should be crashed first to cut one day from the project's duration;how much is added to project cost?
d.Which activity should be the next activity crashed to cut a second day from the project's duration;how much is added to project cost?
e.Assuming no other paths become critical,how much can this project be shortened at what total added cost?


Definitions:

Structural Level

An analysis or approach focusing on the arrangement and organization of components within a system.

Cultural Diversity

The existence of a variety of cultural or ethnic groups within a society, organization, or community.

Cognitive Dissonance

The mental discomfort experienced by an individual who holds two or more contradictory beliefs, ideas, or values at the same time.

Structural Change

Major shifts or alterations in the organizational, economic, or social framework of an entity or society.

Related Questions