A Local Project Being Analyzed by PERT Has 42 Activities,13

question 101

Multiple Choice

A local project being analyzed by PERT has 42 activities,13 of which are on the critical path.If the estimated time along the critical path is 105 days with a project variance of 25,what is the probability that the project will be completed in 95 days or less?