A Project Being Analyzed by PERT Has 38 Activities,16 of Which

question 57

Multiple Choice

A project being analyzed by PERT has 38 activities,16 of which are on the critical path.If the estimated time along the critical path is 90 days with a project variance of 25,what is the probability that the project will be completed in 88 days or less?