The Time Required to Complete a Project Is Normally Distributed

question 134

Multiple Choice

The time required to complete a project is normally distributed with a mean of 80 weeks and a standard deviation of 10 weeks.The construction company must pay a penalty if the project is not finished by the due date in the contract.If a construction company bidding on this contract puts in a due date of 80 weeks, what is the probability that they will have to pay a penalty?


Definitions:

Rights Offering

A financial offering in which a company grants existing shareholders the right to buy additional shares at a discount to the market price before the new shares are offered to the public.

Term Loans

Term loans are monetary loans that are repaid in regular payments over a set period of time, typically used for financing specific assets or projects.

Direct Business Loans

These are loans offered directly from a lender to a business without the use of intermediaries. This can provide more straightforward access to capital for businesses.

Green Shoe Provision

An option that allows underwriters to buy and sell additional shares if the demand exceeds expectations during an IPO.

Related Questions