The following represents a project with known activity times.All times are in weeks.
Table 11-1 The following represents a project with known activity times.All times are in weeks.    -Using the data in Table 11-1, what is the minimum possible time required for completing the project? A) 8 B) 14 C) 25 D) 10
-Using the data in Table 11-1, what is the minimum possible time required for completing the project?