Your company is considering submitting a bid on a major project.You determine that the expected completion time is 150 weeks and the standard deviation is 10 weeks.It is assumed that the normal distribution applies.You wish to set the due date for the project such that there is a 95 percent chance that the project will be finished by this time.What due date should be set?