Consider the Project with the Following Estimates for Activity Times

question 138

Short Answer

Consider the project with the following estimates for activity times and precedence relationships:
Consider the project with the following estimates for activity times and precedence relationships:    (a)What is the expected duration of the project? (b)What is the project variance? (c)If the deadline of the project is 25 days, what is the probability of finishing the project on time? (a)What is the expected duration of the project?
(b)What is the project variance?
(c)If the deadline of the project is 25 days, what is the probability of finishing the project on time?


Definitions:

Purpose

The reason for which something is done or created, or the reason for an object's existence.

Goal Setting

The practice of identifying and outlining personal or professional targets and planning steps to achieve them.

Determine Purpose

The process of identifying the specific reason or intention behind an action or task.

Attend College

The action of enrolling in and going to a tertiary education institution for pursuing higher education or a degree.

Related Questions