Examlex

Solved

Table 11-8 a Mad Scientist Has Identified the Ten Steps Required to Required

question 52

Essay

Table 11-8
A mad scientist has identified the ten steps required to create a race of atomic supermen to complete his plans for world conquest.The estimated time in weeks and cost in US dollars appear in the table along with the shortest possible duration for each activity and cost of those expedited activities.Activities are designated generically as A, B, and so on in order to avoid any copycat projects of this nature.
Table 11-8 A mad scientist has identified the ten steps required to create a race of atomic supermen to complete his plans for world conquest.The estimated time in weeks and cost in US dollars appear in the table along with the shortest possible duration for each activity and cost of those expedited activities.Activities are designated generically as A, B, and so on in order to avoid any copycat projects of this nature.    -Consider the project summarized in Table 11-8.What is the minimum cost project in order to finish in a year? List the activities crashed and the total cost? What is the difference in the total project cost before and after crashing?
-Consider the project summarized in Table 11-8.What is the minimum cost project in order to finish in a year? List the activities crashed and the total cost? What is the difference in the total project cost before and after crashing?


Definitions:

Related Questions