Consider the Project with the Following Estimates for Activity Times

question 138

Short Answer

Consider the project with the following estimates for activity times and precedence relationships:
Consider the project with the following estimates for activity times and precedence relationships:    (a)What is the expected duration of the project? (b)What is the project variance? (c)If the deadline of the project is 25 days, what is the probability of finishing the project on time? (a)What is the expected duration of the project?
(b)What is the project variance?
(c)If the deadline of the project is 25 days, what is the probability of finishing the project on time?