An IT Project Requires 6 Activities

question 9

Essay

An IT project requires 6 activities.The table below displays the expected time and budgeted cost for each activity.
An IT project requires 6 activities.The table below displays the expected time and budgeted cost for each activity.    Develop a budget for the 15 weeks of the project using LS times. Develop a budget for the 15 weeks of the project using LS times.