Given (Time in Weeks): Determine

question 22

Essay

Given (Time in weeks): Given (Time in weeks):     Determine: (a) the critical path. (b) the probability that the project will be completed in 22 weeks. Given (Time in weeks):     Determine: (a) the critical path. (b) the probability that the project will be completed in 22 weeks. Determine:
(a) the critical path.
(b) the probability that the project will be completed in 22 weeks.