Table 12-2
The following represents a project with four activities. All times are in weeks. Table 12-2 The following represents a project with four activities. All times are in weeks.   -According to the data in Table 12-2, what is the critical path? A)  A-B B)  A-C C)  B-D D)  A-B-C-D E)  None of the above
-According to the data in Table 12-2, what is the critical path?