Consider a Project That Has an Expected Completion Time of 50

question 46

Multiple Choice

Consider a project that has an expected completion time of 50 weeks and a standard deviation of 9 weeks.What is the probability that the project is finished in 57 weeks or fewer? (Round to two decimals. )