A Project Requires at Least 28 Worker-Days to Complete the Project.What

question 6

Multiple Choice

A project requires at least 28 worker-days to complete the project.What is the shortest time estimate for completion if the project is constrained to two workers per day? Assume no task requires more than one worker and the tasks can be completed independent of each other.