Calculate the Latest Finish for Task B If Its Predecessor

question 99

Multiple Choice

Calculate the latest finish for Task B if its predecessor, Task A, finishes on day 3, its succeeding activity, Task E, has a latest start of day 7, and the duration of Task B is 2 days.

Comprehend the objectives and impact of the Mission to the Slaves.
Identify the similarities between West African religions and Christianity.
Analyze the importance of religion in mid-19th century reform movements.
Evaluate the challenges faced by reformers in the 19th century.

Definitions:

Activity Cost Pools

Activity Cost Pools are aggregations of all the costs associated with particular activities used in activity-based costing to allocate overhead costs more accurately.

Predetermined Overhead Rates

Rates used to apply manufacturing overhead to products or job orders, calculated in advance based on estimated overhead costs and activity levels.

Activity-Based Costing

A method of costing that identifies activities in an organization and assigns the cost of each activity to products or services according to the actual consumption of each.

Expected Activity

This term refers to the estimated level of operations or production expected to be achieved in a future period.

Related Questions