Calculate the Earliest Start for Task D If One of Its

question 83

Multiple Choice

Calculate the earliest start for Task D if one of its predecessors, Task A, finishes on day 3, its other predecessor, Task C, finishes on day 4, and the duration of Task D is 2 days.