Calculate the Latest Start for Task B If Its Predecessor

question 121

Multiple Choice

Calculate the latest start for Task B if its predecessor, Task A, finishes on day 3, its succeeding activity, Task E, has a latest start of day 7, and the duration of Task B is 2 days.