question 34

Multiple Choice

The total completion time is 25 days.Task A is planned to take seven days.Task B is planned to take five days.Task C is planned to take eight days.The tasks have a serial relationship.Task A takes nine days to be completed instead of seven days.What are the ES and EF times for Task B now that Task A is complete?

Acknowledge the significance of social groups and their influence on individuals.
Understand the effects of postindustrialism on society, including changes in job markets and the importance of education.
Distinguish between ascribed and achieved statuses and comprehend their impact on social identity.
Identify the challenges associated with role conflict and role strain in complex societies.

Definitions:

Indirect Method

A way of calculating cash flows from operating activities in the cash flow statement by adjusting net income for changes in non-cash accounts.

Net Decrease

A reduction in the quantity or value of something, calculated by subtracting the final figure from the initial figure.

Inventories

Quantities of goods that are held by a company for the purpose of resale or production.

Indirect Method

A way of preparing the cash flow statement where net income is adjusted for non-cash transactions and changes in working capital to arrive at operating cash flow.

Related Questions