The Time Required to Complete a Project Is Normally Distributed

question 34

Multiple Choice

The time required to complete a project is normally distributed with a mean of 80 weeks and a standard deviation of 10 weeks.The construction company must pay a penalty if the project is not finished by the due date in the contract.If a construction company bidding on this contract puts in a due date of 80 weeks,what is the probability that they will have to pay a penalty?


Definitions:

Stress

A state of tension caused by extraordinary demands, constraints, or opportunities.

Tension

A state of mental or emotional strain, often resulting from challenging or demanding situations.

Personal Economics

The study of how individuals manage their resources, including money, time, and skills, to meet personal and family needs and goals.

Non-Work Factors

Elements not related to one's job or professional responsibilities, such as personal issues or external activities, that can influence one's performance and well-being.

Related Questions