The Time Required to Complete a Project Is Normally Distributed

question 118

Multiple Choice

The time required to complete a project is normally distributed with a mean of 80 weeks and a standard deviation of 10 weeks.The construction company must pay a penalty if the project is not finished by the due date in the contract.If a construction company bidding on this contract wishes to be 90 percent sure of finishing by the due date,what due date (project week #) should be negotiated?


Definitions:

Macular Degeneration

A medical condition which may result in blurred or no vision in the center of the visual field due to damage to the retina.

Optic Disk

The point in the eye where the optic nerve connects to the retina, also known as the blind spot.

Retina

A thin layer of tissue located on the inside back wall of the eye, containing cells that are sensitive to light and trigger nerve impulses that pass via the optic nerve to the brain, where a visual image is formed.

Lens

A part of the eye that focuses light onto the retina, enabling vision.

Related Questions