Given an Activity's Optimistic,most Likely,and Pessimistic Time Estimates of 4,14,and

question 126

Multiple Choice

Given an activity's optimistic,most likely,and pessimistic time estimates of 4,14,and 18 days respectively,compute the PERT expected activity time for this activity.