Examlex

Solved

Table 11-1 The Following Represents a Project with Known Activity Times.All Times

question 114

Multiple Choice

Table 11-1
The following represents a project with known activity times.All times are in weeks. Table 11-1 The following represents a project with known activity times.All times are in weeks.   -Using the data in Table 11-1,what is the minimum possible time required for completing the project? A) 8 B) 14 C) 25 D) 10 E) None of the above
-Using the data in Table 11-1,what is the minimum possible time required for completing the project?


Definitions:

Related Questions