Table 11-3 -According to Table 11-3,there Are Five Activities in a PERT

question 112

Multiple Choice

Table 11-3 Table 11-3   -According to Table 11-3,there are five activities in a PERT project.If the normal distribution were used to find the probability of finishing this project in 24 weeks or fewer,what mean and variance would be used? A) 20 and 4.222 B) 30 and 5.222 C) 20 and 5.222 D) 30 and 4.222 E) 22.667 and 1.111
-According to Table 11-3,there are five activities in a PERT project.If the normal distribution were used to find the probability of finishing this project in 24 weeks or fewer,what mean and variance would be used?


Definitions:

Body

Refers to the physical structure of an organism or any living entity, comprising systems that perform vital functions.

Living Organism

Any entity that exhibits the characteristics of life, such as growth, reproduction, responsiveness, and metabolism.

Hydrologic Cycle

The continuous cycle of water movement through the Earth's system, including processes such as evaporation, condensation, precipitation, and infiltration.

Fresh Water

Water that contains minimal amounts of dissolved salts, typically found in lakes, rivers, and streams.

Related Questions