Given an Activity's Optimistic,most Likely,and Pessimistic Time Estimates of 3,7,and

question 108

Multiple Choice

Given an activity's optimistic,most likely,and pessimistic time estimates of 3,7,and 11 days respectively,compute the expected time for this activity.


Definitions: