Figure 11-1 -Given the Network in Figure 11-1,the Time to Complete Those

question 32

Multiple Choice

Figure 11-1 Figure 11-1   -Given the network in Figure 11-1,the time to complete those activities on the critical path is expected to be A) 20. B) 22. C) 25. D) 26. E) None of the above
-Given the network in Figure 11-1,the time to complete those activities on the critical path is expected to be