Consider the Following Project Schedule: (A)Which Activities Are Critical

question 41

Essay

Consider the following project schedule: Consider the following project schedule:   (a)Which activities are critical? (b)Which activity has the most slack? (a)Which activities are critical?
(b)Which activity has the most slack?


Definitions: