Table 10-1
A company has decided to use 0-1 integer programming to help make some investment decisions.There are three possible investment alternatives from which to choose,but if it is decided that a particular alternative is to be selected,the entire cost of that alternative will be incurred (i.e. ,it is impossible to build one-half of a factory) .The integer programming model is as follows:
Maximize 5000 X1 + 7000X2 + 9000X3
Subject to: X1 + X2 + X3 ≤ 2 (only 2 may be chosen)
25000X1 + 32000X2 + 29000X3 ≤ 62,000 (budget limit)
16 X1 + 14 X2 + 19 X3 ≤ 36 (resource limitation)
all variables = 0 or 1
where X1 = 1 if alternative 1 is selected,0 otherwise
X2 = 1 if alternative 2 is selected,0 otherwise
X3 = 1 if alternative 3 is selected,0 otherwise
The optimal solution is X1 = 0,X2 = 1,X3 = 1
-According to Table 10-1,which presents an integer programming problem,if the optimal solution is used,what would the value of the objective function be?
A method of exchanging digital messages over the Internet, using a software application to compose, send, store, and receive messages.
Course of Performance
A term in contract law referring to the conduct between contracting parties that is consistent with their agreement, influencing future interpretations of the contract terms.
Course of Dealing
A sequence of actions or conduct between parties in a business or legal relationship that establishes a common basis for understanding future transactions.
Usage of Trade
Established practices, methods, or customs that are widely accepted and utilized in a particular industry or trade.
Q2: A request for quotation (RFQ):<br>A)signals the purchaser
Q6: Supply can simultaneously achieve cost reductions and
Q7: Capital assets:<br>A)have an expected use of less
Q8: Supply's growing involvement in the acquisition of
Q23: As the buyer-supplier network grows in size
Q25: Portfolio or quadrant analysis may be used
Q50: Simulation can use any probability distribution that
Q59: An IT project requires 6 activities.The table
Q74: Table 10-3 presents an integer programming problem.Suppose
Q89: PERT was developed for a project for