Use the S-Curve to Choose the Best Statement About the Project

question 64

Multiple Choice

Use the S-curve to choose the best statement about the project it describes. The horizontal axis is in weeks. Use the S-curve to choose the best statement about the project it describes. The horizontal axis is in weeks.   A)  More time passes from weeks 5 to 10 than from weeks 20 to 25. B)  More time passes from $50,000 to $60,000 than from $5,000 to $10,000. C)  More money is spent from weeks 0 to 10 than from weeks 30 to 40. D)  The total amount spent on the project at the end of the 40<sup>th</sup> week is approximately $110,000.