Use the Earned Value Table for Project Terrace to Calculate

question 10

Multiple Choice

Use the earned value table for Project Terrace to calculate their schedule performance index if all dollar amounts are in hundreds. Use the earned value table for Project Terrace to calculate their schedule performance index if all dollar amounts are in hundreds.   A)  0.90 B)  0.80 C)  1.12 D)  1.20