Use the Earned Value Table for Project Terrace to Calculate

question 23

Multiple Choice

Use the earned value table for Project Terrace to calculate their estimated cost to completion (all dollar amounts are in hundreds) . Use the earned value table for Project Terrace to calculate their estimated cost to completion (all dollar amounts are in hundreds) .   A)  $4,285 B)  $4,800 C)  $4,532 D)  $3,604