Use the Project Described in the Table to Determine the Total

question 51

Multiple Choice

Use the project described in the table to determine the total resources required for activity D if a worker is expected to work half-time (four hours per day) on this project. Use the project described in the table to determine the total resources required for activity D if a worker is expected to work half-time (four hours per day)  on this project.   A)  6 hours B)  40 hours C)  24 hours D)  48 hours