A 14-Week Construction Activity Requires a Crane That Rents for $1,000

question 86

Multiple Choice

A 14-week construction activity requires a crane that rents for $1,000 per week and a crew of general laborers that costs $5,000 per week.In order to complete this activity within 10 weeks,you must hire additional general laborers at a cost of $2,000 per week.What is the slope for this activity?