What Is the Early Start Time for Activity D Given

question 83

Multiple Choice

What is the early start time for Activity D given the activity times and precedence requirements shown in the table? What is the early start time for Activity D given the activity times and precedence requirements shown in the table?   A)  5 B)  9 C)  13 D)  18