Use the Network Diagram and Activity Lengths in the Nodes

question 47

Multiple Choice

Use the network diagram and activity lengths in the nodes to determine the late finish time for activity C. Use the network diagram and activity lengths in the nodes to determine the late finish time for activity C.   A)  12 B)  13 C)  14 D)  15